Second: Services provided in the
field of major projects
1 - Approval of establishing
intensive energy industrial projects outside industrial zones and inside the 27*
areas allocated for heavy industries and the environment polluting
industries
Accomplishment Time :
According to the volume and quality of the project's activity
Competent Authority :
Central Administration for Industrial Services Tel.: 795-3674
Documents required :
• The investor is
to fill out the application form for establishing an industrial project outside
industrial zones (available free of charge). The following documents are to be
submitted:
1 - Basic data of project on IDA's form.
2- 4 cadastral maps of the location
approved by the governorate, indicating the location's coordinates with a scale of 1:25000.
3- Payment of standard costs of
studies, approvals, licenses and issuance of registration certificates in the
industrial registry.
4- An
official exemplification of the company establishment contract (internal
investment system) or investment sheet
indicating payment of 25% of issued capital calculated according to land area X
LE 125 per M2.
5- A general plan indicating distribution of the
activities to be established.
6- A list of the machinery & equipment
used and the relevant catalogs.
* The 27 areas allocated for heavy industries and
environment polluting industries (Badr - Qena, east of Al Shehin Valley - Al
Alaki Valley - Aswan -Mersa Alam - Safaga, Red Sea - N. Sinai - north of Ataka -
south of Ataka - central Eastern Desert - west of Qena - Industrial Zone 21
expansion -El Sadat - Al Tagani Palace - south of Alamin - Matruh - east of
Matruh Desert - Beni Sueif - S. Sinai, Abu Zenima Village - S. Sinai - Al Kabd
Valley - Minya - New Valley - west of Sohag - east of Sohag - Qena - Al Saraya
Mount - Assiut - west of Nag Hammadi)
Approvals required :
1- Submitting an
application to IDA to obtain the land according to the methodology approved by
the Minister
on 19/10/2006 including one of the following
alternatives:
• Land allocation according to a 40-year concession at LE2
per square meter.
• Land allocation in accordance with possession
transfer system at LE50 per square meter and payment of 10% of land price upon
allocation with 3-year grace period and the remainder to be paid by 7 annual
installments at the interest determined by the National Investment Bank.
• Land allocation in partnership with the Ministry of Industry at LE75
per square meter without utilities.
• The Environmental Affairs Agency's
approval of the project's environmental impact study. Approval of the
governorate or the competent authority of utilizing the land for industrial
activity.
• Approval of the two ministries of electricity and petroleum
of supplying the necessary energy.
• Approval of the Armed Forces for
Sinai Peninsula governorates.
2- IDA's affiliate competent
department is to study the project technically according to the standards of
each industry.
3- In coordination with the National
Center for State Land Utilization, IDA finalizes the procedures of land
possession transfer
(project site) to the targeted industry (projects outside industrial
zones).
4- In coordination with the
National Center for State Land Utilization, IDA verifies coordinates of the
project land (projects in the 27
areas)
5- After finishing the technical study and submitting all documents
& approvals, the final approval of the project is to be issued and handed to
the investor.
2- Approval of establishing industrial projects
outside industrial zones on the lands of agricultural reclamation and which are
unfit for cultivation OR close to raw materials and resources that can be
utilized
Accomplishment Time : According to the volume and
quality of the project's activity
Competent Authority : Central Administration
for Industrial Services Tel.: 7953674
Documents required :
• The investor
is to fill out the application form for establishing an industrial project
outside industrial zones (available free of charge). The following documents are
to be submitted:
1 - Basic data of project on IDA's form.
2- 4
cadastral maps of the location approved by the governorate, indicating the
location's coordinates with a scale of 1:25000.
3- Payment of standard
costs of studies, approvals, licenses and issuance of registration certificates
in the industrial registry.
4- A general plan indicating distribution of
the activities to be established.
5- A list of the machinery &
equipment used and the relevant catalogs.
• Site Conditions
1
- The project location should be far from urban and housing areas for a distance
not less than 5km, taking the prevalent wind direction into
consideration.
2- To be close to main roads.
3- Availability of
all necessary utilities on the land allocated for
project.
4- Non-existence of any industrial zone at a distance of
25-30km from the location.
5- Closeness of project to the quarries where
the necessary raw materials are available.
Approvals required
1 - If the project owner possesses the land, the
investor should submit the competent authority's approval.
2- If the project
owner doesn't possess the land:
- The investor is to apply to IDA for
land allocation according to the methodology approved by the Minister on
19/10/2006, including one of the following alternatives:
- Land
allocation by concession for 40 years at LE2 per square meter.
- Land
allocation in accordance with possession transfer system at LE50 per square
meter. 10% of land price to be paid upon allocation with 3-year grace period and
the remainder to be paid by 7 annual installments at the rate determined by the
National Investment Bank.
- Land allocation in partnership with the
Ministry of Industry at LE75 per square meter without utilities.
Ministry of Environmental Affairs' approval of the project's environmental
impact
1 - IDA's competent technical department is to study the project
technically according to standards of each industry.
2- In coordination
with the National Centre for State Land Utilization, IDA is to finalize the
procedures of land possession transfer (project site) to the targeted
industry.
3- Presenting a guarantee letter of 10% of the project's
investments as a financial solvency to be released after ] obtaining the
industrial register (2 years at maximum). The project's investments are to be
calculated according to the project area X LE 125 per square
meter.
4- After finishing the technical study and submitting all the
necessary documents & approvals, the final approval of the project is to be
issued and handed to the investor.
3- Approval of establishing industrial
projects outside industrial zones on the lands of agricultural reclamation
Accomplishment Time: According to the volume and
quality of the project's activity
Competent Authority: Central Administration for
Industrial Services Tel.: 7953674
Documents required :
a) The investor is
to fill out the application form for establishing an industrial project outside
industrial zones (available free of charge). The following documents are to be
submitted:
1 - Basic data of project on IDA's form.
2- 4 cadastral maps of the location approved by the
governorate, indicating the location's coordinates with a scale of 1:25000.
3- Payment of standard costs of studies, approvals,
licenses and issuance of registration certificates in the industrial
registry.
4- A general plan indicating distribution of the
activities to be established.
5- A list of the machinery & equipment
used and the relevant catalogs.
6- Ministry of Agriculture's
approval.
b) Site Conditions:
1 - The project location should be far from urban and
housing areas for a distance not less than 5km, taking the prevalent wind
direction into consideration.
2- To be close to main
roads.
3- Availability of all necessary utilities on the land allocated
for project.
4- Non-existence of any industrial zone at a distance of
25-30km from the location.
5- The land to be possessed by the project
owner.
c) Environmental Conditions:
1 - The Environmental Affairs Agency's
approval of the project's environmental impact study.
2- Determining the
way of industrial drainage waste disposal.
3- Drawing up the project's
industrial security plan.
4- The overall emissions of project should be
within the limits allowed in accordance with Law No. 4 / 1994 and its executive
regulations.
d) Project Conditions:
1 - To be mainly based on farm crops (vegetables -
fruit - grains - ...etc) in production. 2- To be close to the raw materials
necessary for establishing the project.
e) Other Conditions:
1 - Presenting an undertaking by the person concerned
that he will not dispose of the project by sale, waiver or rent before 10 years
from the date of production start.
2- Presenting a guarantee letter of
10% of the project's investments as a financial solvency to be released after
obtaining the industrial register (2 years at maximum). The project's
investments are to be calculated according to project area X LE 125 per square
meter.
3- IDA's competent technical department is to study the project
technically according to standards of each industry.
4- After finishing
the technical study and submitting all the necessary documents & approvals,
the final approval of the project is to be issued and handed to the
investor.